Building sites
31 March 2026
Last update 22/04/2026 à 11h12
The work in brief
- Work to repair the rear roof of the Michel-Normandin arena will start the week of April 13, and will last approximately 10 weeks, depending on weather conditions.
- Work will include re-roofing, as well as adjustments to equipment and drainage systems.
- During the works, measures will be put in place to secure the area around the building. All access to the arena will be maintained.
Timetable
April to July 2026
Investment
This major project, representing a municipal investment of $697,000, aims to ensure the building’s longevity and maintain quality facilities for users.