Infrastructure
01 April 2025
Last update 21/07/2025 à 14h26
Progress schedule
Between Parc de la Terre and Route Verte
PlanifiéType of work
Creation of a bicycle path on rue Tisserand, between Parc de la Terre and Route Verte.
Obstacles / Impacts
August 5 to mid-October
- Occasional evening and night closures of the right-turn lane of exit ramp no. 8 (Boulevard Taschereau/La Prairie/Longueuil) from autoroute 10 westbound to boulevard Taschereau eastbound. Vehicles must turn right at traffic lights. Trucks will have to take a marked detour since the turning radius will not be sufficient. The detour will take in boulevard Taschereau west, boulevard Matte west, boulevard Marie-Victorin east and autoroute 10 east, before returning to route 134.
- Evening and night closures of one or two of three eastbound or westbound lanes of Route 134 between the Autoroute 10 service road and Panama Avenue.