Type of work
Construction of a new sanitary duct between avenue de l’Équateur and rue des Éléments.
Work carried out by developer Édyfic Construction.
Timetable
Phase 1 (pipeline construction): approx. March 24 to April 4, 2025
Phase 2 (completion of work): around May 2025
Obstacles / Impacts
During the work, the eastbound lanes of boulevard du Quartier, between avenue de l’Équinox and rue des Éléments, will be completely closed to traffic. Two out of three westbound lanes will remain open at all times. Motorists travelling east on boulevard du Quartier will have to take boulevard Lapinière, boulevard Chevrier, then Grande Allée.
Documents
Letter to residents (03/17/2025)
Notice of works (14/03/2025)
Progress schedule
Phase 1: Pipe construction
En cours March 24 to about April 4, 2025Phase 2: Completion of work
Planifié Around May 2025