Progress schedule
Phase 3
Planifié UndeterminedProject summary
- Complete refurbishment of the synthetic football/soccer pitch
- Complete refurbishment of the athletics track
- Rehabilitation of Neuville access road
Phase 2
En cours 2025-2027Project summary
- New reception pavilion
- New central public square incorporating a cool-down area (jets and misters)
- Repair of part of the parking lot and addition of a landing stage
- Construction of a new cricket pitch (1)
- Repairs to part of the bike path on avenue Niagara
- New network of pedestrian and bicycle paths in the park
- New outdoor rink with basketball courts (2)
- New slide mound
- New free skating area
- Street furniture
- Diversified planting (trees, shrubs, herbaceous plants)
- Biodiversity zone
Phase 1B
En cours 2024-2025Project summary
- Construction of new Pickleball courts (6)
- Construction of additional tennis courts (2)
- Vegetated retention basin
- Relaxation area
- Repairs to part of the bike path on avenue Niagara
- Repair of part of the parking lot
- Refurbishment of the area dedicated to the Wall Ball, including lighting and fencing
- Street furniture
- Diversified planting (trees, shrubs, herbaceous plants)
Sequence 1
Excavation and installation of a concrete pad and access shafts in the park for Hydro-Québec and Bell Canada’s urban technical networks.
The Poly-Aréna park bike path will not be accessible during the work.
Status : Completed
Sequence 2
Construction of a new bike path on rue Niagara and a new entrance to the park parking lot.
Work on the new entrance to the car park has been moved to sequence 3.
Status : Completed
Sequence 3
Development of new pickleball and tennis courts and surrounding green spaces.
Status : In progress
Sequence 4
Rehabilitation of infrastructure and parking behind Michel-Normandin arena, as well as along the tennis courts resurfaced last summer (phase 1A).
Status : In progress
Phase 1A
Terminé Summer 2024Project summary
- Complete renovation of tennis courts (6), including lighting and fencing
- Creation of a vegetated retention basin
- Adding street furniture
- Diversified planting
The municipal council awarded a contract to Gestion Dexsen inc. to carry out work on phase 1A of the redevelopment of Poly-aréna park, following a public call for tenders that closed on July 13, 2023.
The first phase of this major project will begin in early October 2023, kicking off the implementation of the Functional and Technical Plan (FTP) developed to complement the Master Plan for Public and Recreational Facilities.
This phase of the project is scheduled for completion in summer 2024.
The work represents an investment of $1.6 million, some 20% below the initial estimate.
In the press release of August 24, 2023 announcing this first phase of development, Doreen Assaad, Mayor of Brossard, declared: “Parc Poly-aréna is the city’s most important sports hub. Dedicated to the practice of various activities on a variety of outdoor platforms, it is also a prime gathering place for festive events. Our ambition is to adapt to the needs of the population by placing them at the heart of our town’s development. The council and I are extremely proud of the major projects underway throughout our territory. We’re building the Brossard of tomorrow, and we can’t wait to see our city grow and change.
Find out about the three other phases planned over the next few years.