Progress schedule

Phase 5

Planifié 2026-2027
  • Illuminated bicycle and pedestrian network
  • Street furniture and planting
  • Service building
  • Tennis and pickleball courts
  • Intergenerational exercise area

Phase 3B

Terminé 2024-2025

Phase summary:

  • Illuminated bicycle and pedestrian network
  • Street furniture and planting
  • Disc golf course
  • Creation of micro-forests
  • Landscaping and lighting for the permanent retention basin

Phase 3A

Planifié 2028-2029

Phase summary:

  • Refrigerated outdoor rink with roof and basketball courts
  • Service building
  • Street furniture and planting

Phase 2 - Completed

Terminé Summer 2023

Phase summary:

  • Playground
  • Water games
  • Outdoor pavilion
  • Bike stop
  • Pond improvement
  • Illuminated bicycle and pedestrian network
  • Street furniture and planting

Phase 1A - Lapinière sector - Completed

Terminé

Phase summary:

  • Training circuit
  • Sliding hill
  • Rest areas
  • Bicycle and pedestrian networks
  • Main and secondary entrances
  • Planting and landscaping
  • Sidewalks in both directions

Phase 1B - Eastern sector - Completed

Terminé

Following an extensive citizen consultation process between 2015 and 2016, in 2018 the Ville de Brossard began the creation of an urban park of over 4 million square feet. This large green space, unique in its size and natural environment, offers a variety of activities for all citizens, all year round.

A space for everyone:

  • Illuminated bicycle and pedestrian network
  • Street furniture and planting
  • Disc golf course
  • Creation of micro-forests
  • Landscaping and lighting of the permanent water retention basin
  • Service building
  • Playground and water games
  • Outdoor pavilion
  • Bike stops
  • Training circuit
  • Sliding hill for winter activities
  • Rest areas

The park is accessible via several entry points and features sidewalks in both directions for smooth, safe traffic flow. Improved ponds and landscaping help make the park an essential place for relaxation

Phase summary:

  • Retention basin with permanent water retention
  • Access via rue Condor
  • Bicycle and pedestrian networks